Pavement Program

The City of Piqua maintains nearly 111 centerline miles of publicly owned and maintained roadway which equates to 0.67 square miles, or over 18.6 million square feet, of pavement area. 

Maintenance and rehabilitation on the City’s pavement network is performed annually to address streets that are in poor condition and to extend the service life of streets in good condition. 

Streets are one of the City’s most valuable assets with a replacement value estimated at approximately $27.5 million to mill and overlay every street.

Program Benefits

  • Inventory management of all streets maintained by the city.    
  • Current and historical record of documentation of all maintenance and rehabilitation treatments performed by the City.    
  • Strives to maintain an overall Pavement Condition Index (PCI) of 70 or better.  PCI of 70 and above are considered good to excellent condition.    
  • Identifies and generates a recommended Annual Street List to maximize results based on existing conditions and available funding.     
  • Implements required  ADA and Curb Ramp Improvements to meet current standards.       
  • Striping Plan review by Engineering Manager to identify opportunistic roadway striping improvements to enhance Mobility and Traffic Safety.    

PCI Information (Available soon)

GIS Road Conditions Map (Available soon)

Pavement Program (GIS Page)

  1. Kenton Kiser

    Engineering Manager

  2. Gavin Miller

    Engineering Tech III

  3. Emily McCulla

    Administrative Assistant

Physical Address

201 W Water Street
2nd Floor
Piqua, OH 45356

Directions


Phone: 937-778-2049 

Program Facts / Data

The City of Piqua continues to invest in its roadways, alleys, and pavement.  We also continue to improve the overall ADA compliance of our roadways and intersections with the construction and replacement of ADA curb ramps annually.


2026 (Current)
2025 (Last Year)
2020-2024
Roadway Centerline Miles Treated
TBD5.7125.33
Alley Centerline Miles Paved
TBD4.353.45
ADA Ramps Replaced
TBD71231
Total Expenditure
TBD
$1,549,454.81
$5,993,187.31